ICEA P-45-482 · BS 8010-2.1

Calculate pulling tension and sidewall bearing pressure for cable installation in ducts and conduits. Define multi-section routes with straight runs, bends, and inclined sections.

T_out = T_in × e^(μθ) at bends (capstan equation)• T = μWL for straight sections• SBP = T / R (N/m)• Conduit fill & jam ratio checks
Cable & Conduit Properties
Allowable Limits

Typical Cu conductor: 16,800 N for 240 mm² × 1 cable(s)

Route Definition
TypeLength / AngleDirection / RadiusIncl. °
°
m R

Define your cable route

Add straight sections and bends, then calculate

Based on ICEA P-45-482 and BS 8010-2.1. Friction coefficients and SBP limits are typical values — always obtain manufacturer-specific data for the cable type being installed.